Programme
The Selkirk FPS Project Programme is a live document and is used by the
Project Team to monitor the project's progress. The Project Programme is
very large and includes a line for each activity to be undertaken. This
stretches from the Project Kick-Off Meeting on 15th October 2009 until the
as yet undetermined date when everything is complete.
The Selkirk FPS has been broken into 8 distinct stages. These 8 stages
allow for the logical grouping of activities that require to be completed
during the life of the scheme. In general the stages are designed such that
they are completed one after the other however the Project Team advanced
parts of Stage 2 and Stage 3 simultaneously. This was to deliver greater
efficiency and to shorten the total length of the programme.
This Project Programme is updated as often as required to allow for full
control of the project's many activities. It is fully updated on a monthly
basis as part of the quality control and project management processes.
The Stage Programme
Because of the size, complexity and duration of the live Project Programme
the Project Team have designed a simplified programme which details the
main stages of the project. To view the most recent version of this programme
please click the image below.
The following points are worth noting:
- Stage 1 of the Project was completed on 15th October 2009
when Stage 2 commenced
- Stage 2 of the Project was completed on 20th January 2011
- Stage 2 and Stage 3 were essentially run concurrently to
deliver efficiencies and reduce programme length
- Stage 3 has not yet formally closed but is currently programmed
to be completed on 25th May 2011
- Stage 4 commenced on 21st January 2011
- The current programme identifies real targets for Stage
4 and Stage 5
- The latter part of Stage 5 involves approval of the Selkirk
FPS under the Flood Risk Management (Scotland) Act 2009 (more
details). This is a statutory process and therefore out of the control
of the Project Team. In the event of a valid formal objection the scheme
approval could take years. The Project Team are therefore not prepared to
commit to real targets from this point onwards
- The programme has identified possible timescales for Stages
6, 7 and 8 for illustration purposes only
The Programme for Stages 4 & 5
The Project Team have also designed a simplified programme detailing some
of the main activities in Stages No. 4 and 5. These are the stages that
are of most relevance just now and these are the activities that will hopefully
see us through to scheme approval by December of this year. To view the
most recent version of this programme please click the image below.
Show / Hide older programme information
Over the next few months we will be carrying out the following activities:
| Date |
Description |
| July 2010 |
Use the results of the public exhibition
and further technical assessment to pull together the proposals into
a preferred Scheme. Continue with ecology surveys. |
| August 2010 |
Continuation of scheme option selection
and appraisal. Undertake more consultation with relevant landowners,
public and stakeholders to ensure the proposals are acceptable. |
| September 2010 |
Preferred Scheme report drafted
and approvals process begins. This is the most important part of the
project in terms of what flood protection measures will actually form
the Scheme and the process will therefore take several weeks. St Mary’s
Loch Working Group convened for the first time to specifically discuss
the impacts and issues relating to the potential for using the Loch
to store floodwater. |
The chart below gives an indication of the timescales for the overall
implementation of the flood protection scheme.

This website will be updated regularly and brochures and newsletters will
be circulated in Selkirk at important times in the project's development.