Public Exhibition No. 1
The Project Team undertook two days of successful liaison
with the general public in Selkirk's Victoria Hall on Wednesday 9th and
Thursday 10th June. This was the first of two public exhibitions to be undertaken
as part of the scheme design. The exhibition, titled 'A Review of the Options',
allowed the Project Team to present the many viable options available to
project Selkirk from a 1 in 200 year (plus climate change allowance) flood
event.
On the Wednesday evening, Conor Price (SBC Project Manager) and Steven Vint
(Halcrow Design Manager) held a joint presentation to an open meeting. The
meeting was independently chaired by John Smail of Selkirk and was attended
by approximately 60 people. A question and answer session followed the presentation
allowing the people of Selkirk a chance to ask specific questions about
the Scheme.
At the end of the exhibition an exhausted Conor Price commented that “overall
the exhibition was well received. The clear consensus from the people of
Selkirk was that a scheme is very much desired. There were a number of challenging
arguments put to myself and the rest of the Project Team which we will require
to assess in the coming weeks. For example, the means through which we protect
the Lindean area; and ensuring our scheme does not impact on the Selkirk
Common Riding were two of the issues we will require to consider further.”
A copy of the presentation and the information boards from the exhibition
are available to download on the right hand side of this page. All comments
are welcome and we would appreciate if you could complete a questionnaire
after considering the options.
Analysis of the public's comments
The Project Team have been ongoing with the Option Appraisal
Process since the Public Exhibition in June. In particular, they have been
analysing comments and issues identified through both the completed questionnaires
and the public presentation with questions & answers session.
As part of the systematic approach the Project Team is taking to reviewing
the Options for the Scheme each public comment was identified and considered
within the ongoing Option Appraisal Process. This process is documented
in a report generated by the Project Team.
Report - Formal Review of Feedback
A copy of this report is available for you to download here:
It must be noted at this point that the Option Appraisal Process is an ongoing
activity. As such the Project Team's consideration of the public's comments
is also an ongoing activity. Within the report, on pages 4 to 7, the final
column of the spreadsheet is not yet completed. This is in recognition of
the fact that the Project Team has yet to close out consideration of comments.
If you have any comments on the Report or our interpretation of your comments
please get in contact with the Project Team. (leave
Feedback)
Documents
Download poster![]()
Download leaflet![]()
Download presentation![]()
Download welcome board![]()
Download board 1![]()
Download board 2![]()
Download board 3![]()
Download board 4![]()
Download board 5![]()
Download board 6![]()
Download board 7![]()
Download board 8![]()
Download board 9![]()
Download board 10![]()
Download board 11![]()
Download board 12![]()
Download board 13![]()
Download board 14![]()
Download board 15![]()
Download board 16![]()
Download board 17![]()
Download final board![]()
Download questionnaire![]()